6561/2022 |
2022-12-19 |
WASA |
40 (b) |
Installation of 2028m of 100mm (4") PVC Distribution main and associated appurtenances in Mt. Lambert. This comprises of eight (8) parallel streets (1st,2nd,3rd,4th,5th,6th,7th,8th streets) between First Avenue and Second Avenue |
Along 1st, 2nd, 3rd, 4th, 5th, 6th, 7th & 8th, Mt. Lambert |
CEC ISSUED 19-Jan-2023 |
|
|
6562/2022 |
2022-12-19 |
WASA |
40 (b) |
Installation of 2060m of 100mm Polyvinyl Chloride (PVC) pipeline and its appurtenances including bridge/culvert crossings and road reinstatement along Riverside Road, St. Augustine |
From the corner of Riverside Road and Eastern Main Road, Curepe to the corner of Riverside Road and Maracas Royal Road, Maracas, St. Joseph |
CEC ISSUED 20-Jan-2023 |
|
|