6100/2020 |
2020-10-06 |
The National Gas Company of Trinidad and Tobago Limited (NGC)
|
27 |
The installation of a 50.8 mm (2-inch) natural gas pipeline, 135 m in length |
from the tie-in point at the National Gas Company of Trinidad and Tobago Limited’s existing 102/76 mm (4/3-inch) pipeline along the Priority Bus Route to Caribbean Packaging Industries Located at Champ Fleurs |
CEC ISSUED
09-Apr-2021 |
|
|
6101/2020 |
2020-10-06 |
Brian Hackett c/o NLBA Architects |
8© |
the clearing, excavation, grading and excavation of land with a gradient of 1:4 or more to facilitate the establishment of a single family residence |
Lot #34 Wellsprings, Cascade Main Road, Wellsprings Development, Cascade |
Clarification Letter 23-May-2022 |
|
|